How Much Does a Yard of Gravel Weigh? Tons per Cubic Yard

Typical weights for gravel and crushed stone per cubic yard, how to turn yards into tons, and how many tons a driveway or path needs.

Quarries often price gravel by the ton, while you measure your project in feet. To connect the two you need the weight of a cubic yard of stone.

To get the tons for your own project, use the gravel calculator.

Try the Gravel Calculator. Tons and cubic yards of gravel or stone

Open the calculator

The short answer

Most gravel and crushed stone weighs about 1.4 tons per cubic yard, which is roughly 2,800 pounds. The usual range is 1.3 to 1.5 tons. The exact weight depends on:

  • The rock. Some rock types are denser than others.
  • Stone size and shape. A mix of sizes packs tighter and weighs more than stones of one size, because small pieces fill the gaps.
  • Moisture. Wet stone weighs more.

Your supplier can tell you the weight of their exact product. Use that number when you have it.

Cubic yards to tons

Tons = cubic yards × tons per cubic yard
Cubic yards Tons at 1.3 Tons at 1.4 Tons at 1.5
1 1.3 1.4 1.5
2 2.6 2.8 3.0
5 6.5 7.0 7.5
10 13.0 14.0 15.0

Going the other way, one ton at 1.4 tons per yard is about 0.71 cubic yards.

Advertisement

Example: a gravel driveway

A driveway is 60 feet long and 12 feet wide, with 4 inches of gravel.

  1. Volume: 60 × 12 × (4 ÷ 12) = 240 cubic feet
  2. Cubic yards: 240 ÷ 27 = 8.89
  3. Tons: 8.89 × 1.4 = 12.4 tons
  4. With 10% extra for compaction: about 13.7 tons

How far a ton of gravel goes

At 1.4 tons per cubic yard, one ton covers about:

Depth Area per ton
2 inches 116 sq ft
3 inches 77 sq ft
4 inches 58 sq ft
6 inches 39 sq ft

Short tons and metric tonnes

In the US, a ton usually means a short ton of 2,000 pounds. A metric tonne is 1,000 kilograms, about 2,205 pounds. If a supplier quotes in tonnes, multiply short tons by 0.907 to compare.

Tips before you order

  • Ask whether the price includes delivery and spreading.
  • Check the truck's minimum and maximum load. Small orders may cost more per ton.
  • For a new driveway, plan a base layer of larger stone and a top layer of finer stone, and work out each layer separately.

For soil and mulch, which are sold by volume, use the cubic yard calculator.